V/Line crews will carry out bridge maintenance and upgrade works in Castlemaine from
Monday 10 February to Monday 10 March.
What we are doing
V/Line is completing necessary maintenance on the historic Midland Highway and Forest Creek bridges in Castlemaine. These works will ensure both bridges continue to provide a vital connection for passengers on the Bendigo Line.
Works schedule
Monday 10 February to Saturday 22 February |
Day works only – between 6.00am and 6.00pm |
Sunday 23 February to Tuesday 25 February |
Day and night works – around the clock |
Wednesday 26 February to Monday 10 March |
Day works only - between 6.00am and 6.00pm |
What to be aware of
There will be regular movement of heavy machinery and trucks, and a significant amount of dust is expected at the work sites.
There will also be a high level of construction noise during the day and when night works are completed from Sunday 23 February to Tuesday 25 February.